Ukrainian nuclear power plants (NPPs) produced 237.60 million kWh of electricity on March 11, the press-service of Ukraine’s State Enterprise “National Nuclear Energy Generating Company Energoatom” reports.
On March 12, 11 out of 15 power units were functioning at the Ukrainian power plants. It was the 52nd day of average planned repairs at power unit No. 2 and the second day of t average planned repairs at power unit No. 4 of Zaporizhzhia NPP. Also, it was the 95th day of average planned repairs at power unit No. 3 of Rivne NPP, and the 32nd day of average planned repairs at power unit No. 2 of South-Ukraine NPP.
Radiation, fire-prevention and ecological state on industrial sites of NPPs are within normal limits. (Ukrinform/Business World Magazine)